RS10BN KARACHI PACKAGE SCHEMES COMPLETION BY DECEMBER
CM approves remodeling of Drig road and Baloch colony flyovers
KARACHI (Aug 2): Sindh Chief Minister Syed Murad Ali Shah reviewing 21 development schemes of Rs10 billion Karachi package has directed local government department to submit their PC-1 documents with P&D department by tomorrow and get them approved from technical committee and provincial Development Working Party (PDWP) so that they could be completed by December 2016.
He issued these directive while presiding over a meeting here at the CM House today. The meeting was attended by Local Government Minister Jam Khan Shoro, Chief Secretary Siddique Memon, Principal Secretary Alamuddin Bullo, ACS (Dev) Mohammmad Waseem, Commissioner Karachi Aijaz Khan, Administrator Karachi Laiq Ahmed, Secretary Finance Hassan Naqvi, Secretary P&D Rehana Memon and others.
Briefing the chief minister ACSS (Dev) Mohammad Waseem said that Rs10 billion Karachi package has 21 schemes. These schemes are to be completed during the current financial year. On this the chief minister said that he would provide necessar funds but schemes must be completed by December 2016.
Briefing about Shaheed Benazir Bhutto Flyover at Shaheen Complex, the ACS (Dev) said it its construction cost is Rs754 million. It would be 400 meter. Its completion time is eight months from date of start.
On this the chief minister asked the project director if he had submitted the PC-I with P&D. The PDs reply was in negative. The chief minister directed him to submit the PC-I by tomorrow and also urged the ACS(Dev) Mr Waseem to hold Technical committee meeting on Friday to approve the scheme. "I want you {PD} to start working on shifting the utilities of KE, SSGCC, water board and such others.," the approval of the schemes and shifting of the utilities must be done simultaneously so that it could be completed before December," he said.
Briefing on the construction of University Road from Hassan Square to Nipa, the ACS (Dev) said it is a Rs995 million scheme and its total length comes to 3.5 kilometer while its width is 16.1 meter, Both the tracks. The chief minister directed the PD to submit its PC-I in the P&D department by tomorrow and take it up in the Technical Committee meeting on Friday. The chief minister said that the road must have drains on both the sides.
Talking about construction of University Road from NED to Safora Chowk, the ACS (Dev) said that it was a Rs780 million scheme. The length of road is 4.5 kilometer with two meters footpath, drainage, LED lights. Its PC-I has been submitted with the P&D. It is supposed to be completed within next six months. The chief minister directed P&D department to approve this scheme in the technical committee meeting being held on Friday.
Discussing Rehabilitation/reconstruction of Tariq Road from Shaheed-i-Millat Road to Shahrah-i-Qaideen, the chief minister was told that it was a Rs523.2 million scheme. Its length is 2.1 kilometer.